Scope of Supply/Work

Copy

Scope of Supply/Work

ItemBROADCustomerRemarks
Transportation and location
Factory to port✓BROAD can arrange transportation upon request.
Port to jobsite✓
Jobsite handling (main shell, pumpset)✓
Joint (for split shipment)✓Welding machine and nitrogen to be provided by customers. Joint process is a paid service.
Electric engineering
Power supply to enclosure✓3 phase, 4 wires
Internet connection✓Network cable to the enclosure is to be provided by users.
Grounding✓Place special grounding terminal with grounding resistance ≤4Ω near water system control cabinet
Construction & installation
Foundation✓Enclosure should be installed after foundation is completed.
Installation of metal enclosure✓
Pipe connection between chiller and pumpset✓For ≥BY400 model, a crane must be provided by customer.
Water softener installation✓Optional
Pipe connection between chiller and cooling tower✓
External piping installation✓Includes chilled/heating water pipes, hot water pipes, water make-up and drain pipes, energy source pipes.
Chiller insulation✓Factory-mounted.
Piping insulation in enclosure✓
Pipeline insulation✓
Antifreezing✓Water anti-freeze treatment is recommended when the ambient temp is below 0°C.
Commissioning
Jobsite chiller commissioning✓Customer provides energy and air conditioning load. Chiller commissioning is a paid service.
Operation & maintenance
Operator training on site✓BROAD provides professional training for free, the customers pay for the accommodations and transportation of BROAD engineers.
Regular maintenance✓Service contract can be signed after the warranty period.